• The base course is in from Higbee Mill to Station 42+00
• All CBI's have been installed on east side from Higbee Mill to Merrimac
• Continued hoe ramming east side at Station 49+83

This week Contractor will continue to hoe ram on east side.  Base asphalt will be placed from Station 42+00 to Merrimac next week weather permitting. After the asphalt is in then Contractor will temporarily stripe the road for winter. The center section of the road will be striped for 2 lanes and barrels will be placed on the outside lanes. Additional work such as storm sewer and conduit will be laid during the winter months.

October 31 - November 3
• Placed DGA from Gravis Ct. to Cromwell for curb and gutter installation
• Finished Wall #4 and #5. (Redi-Rock Wall)
• Hoe ramming still continuing on east side at approx sta. 47+83
  
This week will install curb and gutter, install CBI and storm sewer. Will also include hoe ramming for storm sewer on east side.

October 24-29

• Installed 4 CBI’s 
• Built up superelevated section from Graviss Court to Cromwell
• Hoe ramming still continuing on right side      

Will install curb from Graviss Court to Cromwell
Start on Retaining Wall # 5 this week.

October 17-21

• There were 2 rain days last week.
• Placed CBI’s @ Stations: 39+54 
• Finished Retaining Walls #2, #3 and #4   
• Hoe ramming still continuing on right side at approx Sta. 47+00

Will start on Retaining Wall # 5 this week.

October 10-14
• Placed CBI’s @ Stations: 41+40 lt, 46+66 rt, 39+88 lt
•  Placed approximately 400 Linear Feet of Redi-Rock Wall
• Telephone pole relocated and facilities transferred 
 
Contractor still in rock on the right side where main storm line trunk is located.  Majority of work this week was related to the Redi Rock walls that are being installed. Work this week on the walls and installing storm sewer pipe.

October 3-7
Contractor still in rock for storm sewer.  No estimated time frame for getting out of the rock.
Contractor excavating footers for retaining wall at Graviss Court.  
This week Contractor will continue hoe ramming rock and excavating footers for the wall.

JULY 9- JULY 17 UPDATE
The Contractor accomplished the following last week: 

• Poured curb on east side from Higbee Mill to Graviss Court.

Poured box culvert headwall 

continued laying the 48" RCP

continued working on the curb boxes and catch basins. 

started digging for the footer of the retaining wall near Graviss Court  

This week the contractor will continue to lay more pipe, start working on the concrete gravity wall on the east side of CMR and start the installation of the Redi Rock wall on the west side. 

I would also like to report that Terry Justice, Resident Inspector will be retiring at the end of the month. Terry has done an excellent job for the LFUCG but has decided to start a new career as the lacrosse coach for the Transylvania Pioneers. Terry's replacement will be Darrin Wallingford. Darrin has over 15 years of construction experience and will maintain the same level of service and oversight that we received from Terry. We wish Terry the best and look forward to working with Darrin. Darrin can be reached at http://www.lexingtonky.gov/index.aspx?page=2743859.983.4717 cell.  

JUNE 27- JULY 1 UPDATE
The Division of Engineering is going to be providing weekly updates on the progress of the Clays Mill Road Project for your benefit. Last week was a productive week. The Contractor accomplished the following: 

Completed DGA placement and laid asphalt base for the temporary road widening.

Placed 3 box culvert sections for the 18’ culvert extension. Poured the concrete connection between the existing and new culvert interface.

Completed work on installing catch Basins between Higbee Mill and Graviss Ct.

Started placing DGA for permanent road widening at Lt. STA 26+25 (Westside of CMR at Higbee Mill)

Continuing to lay 48” RCP on eastside of CMR and set catch basin boxes.

This week the contractor will install another super modified box and will place DGA for the curb from Higbee Mill to Graviss Ct. He will continue to work on the headwall for box culvert.


JUNE 21, 2011 UPDATE
Sunday night at 1:30 am our inspector was called out to the site to investigate a trench that had opened up and created a 2- 4 inch depression across Clays Mill Road. The gravel in the trench had washed out as a result of the rains Sunday morning. This has caused numerous flat tires and bent wheel rims. If you get any calls please direct them to Woodall Construction at 223.2909.  The LFUCG is not responsible for any claim. 859.983.4717859.983.4717859.983.4717859.983.4717

The Clays Mill Road Project has been stalled because of the record setting spring rains and utility conflicts which were unforeseen until the contractor was on-site. All of these issues have been resolved and the contractor was back on the job site Monday,June 13.  Also, expect temporary lane closures on Clays Mill Road, near Higbee Mill Road, as early as next week in order to install a storm sewer pipe. Once the temporary lane closures are confirmed you will be notified with at least a 3 day notice. 


If you have any questions, please call Terry Justice through LexCall at 3-1-1 or email him at terryj@lexingtonky.gov.


JUNE 16, 2011 UPDATE
The Clays Mill Road Project has been stalled because of the record setting spring rains and utility conflicts which were unforeseen until the contractor was on-site. All of these issues have been resolved and the contractor was back on the job site Monday,June 13.  Also, expect temporary lane closures on Clays Mill Road, near Higbee Mill Road, as early as next week in order to install a storm sewer pipe. Once the temporary lane closures are confirmed you will be notified with at least a 3 day notice.  


If you have any questions, please call Terry Justice through LexCall at 3-1-1 or email him at terryj@lexingtonky.gov.

MARCH 4, 2011 
RESIDENTIAL MAIL BOXES AND MAIL DELIVERY DURINGCONSTRUCTION
 
Dear Clays Mill neighbors,
Within the next week to 10 days in preparation forconstruction of the Clays Mill widening project, your personal mailbox will becarefully removed and placed on your property. Prior to removing your mailbox, the USPS (United StatesPostal Service) will be erecting a community mail box station on Merrimac Drivenear the intersection with Clays Mill in front of the United Pentecostal Churchat 3416 Clays Mill Road.  The USPS will be providing you an envelope with (3)keys to your individual mailbox at the community mailbox location.  It will benecessary for you to retrieve your mail here for the next 8 or 9 months whilework on the project is taking place.

Please call Terry Justice with the LFUCG at 859-258-3410 ifyou have any questions or concerns.

Sincerely, Woodall Construction Co. Inc.